How to Calculate the Overall Machine Efficiency of Apparel Industries
How to Calculate the Overall Machine Efficiency of Apparel Industries
How to Calculate the Overall Equipment/Machine Efficiency (OEE) of Garments Industries
Joyankar Mojumder
Inspector
Modern Testing Services (BD) Ltd.
280, East Narshinghpur, Ashulia, Savar, Dhaka.
Email: mozumderjoy@yahoo.com
Joyankar Mojumder
Inspector
Modern Testing Services (BD) Ltd.
280, East Narshinghpur, Ashulia, Savar, Dhaka.
Email: mozumderjoy@yahoo.com
What is Overall Equipment/Machine Efficiency (OEE):
OEE is the framework for measuring the efficiency and effectiveness of a process, by breaking it down into three constituent components (Availability, Performance and Quality product rate). It helps to measure a problem so that easily can fix it and provides a standardized method of benchmarking progress. OEE identifies the percentage of planned production time that is truly productive.
OEE= Availability X Performance Rate X Quality Product Rate
Where,
Loading time – Down time
Availability = ………………………………………. X 100
Loading time
Standard cycle time x Processing quantity
Performance = …………………………………………………. x 100
Operating time
Processing quantity – Defective quantity
Quality product rate = ……………………………………………………………. X 100
Processing quantity
Let,
- Working hours per day: 10 hours x 60 min = 600 min
- Shut down (SD): 35 min
- Loading time: (600-35) = 565 min
- Equipment stoppage/ down time: (30+20+25) = 75
(b) Set up : 20 min
(c) Adjustment : 25 min
- Operating time : (565 - 75) = 490 min
- Standard Cycle time : 0.35 min/ pieces
- Processing quantity : 550 pieces/ day
- Defective : 30 pieces.
Loading time – Down time
Availability = ……………………………………………. X 100
Loading time
565 – 75
= ………………….. x 100
565
= 86.72%
Standard cycle time x Processing quantity
Performance = ………………………………………………….. x 100
Operating time
0.35 x 550
= ……………………. X 100
490
= 40.35%
Processing quantity – Defective quantity
Quality product rate = ……………………………………………………………………. X 100
Processing quantity
550 – 30
= …………….. x 100
550
= 94.54%
So, OEE = Availability X Performance Rate X Quality Product Rate
= 0.8672 X 0.4035 X 0.9454
= 33.08%
Low Machine efficiency rate due to man:
- Management Losses;
- Motion Losses;
- Adjustment Losses;
- Losses resulting from lack of automation and
- Monitoring Losses
More articles of this writer:
- Industrial Engineering Formulas for Textile Students and Professionals
- Line Balance and Bottleneck in Garments Production Line
- Introductory of Inspection in Garments Industries
No comments